Our Town Administration building was delivered on September 8th and placed on its foundation on September 9th.  The Roof will be in place by the 11th of September. Our building will soon be looking sharp after the siding, porch and dormers are installed.  We expected the exterior to be completed by the middle of October; unfortunately, the work on the Town’s Administration Building has stalled as two concrete crew members have tested positive for COVID 19 and the whole crew is quarantined.  We have a replacement crew beginning work on the front porch next week and we will be scheduling our move to our new home shortly after its completion.

The Town is beginning the refurbishment of our Town Council Chambers in November.  The new chambers will accommodate additional seating, a new dais, updated sound system and a refurbished bathroom facility, new paint and flooring.

Click here for more project updates.