TLOV-2020-01: S. Church St. & E. Pennsylvania Ave. Streetscape Improvements

Project Status
Complete
Project ID
TLOV-2020-01
Project Type
Capital Improvements

2 Town Square
Lovettsville, VA 20180

Map of Project

Description

PROJECT DESCRIPTION:         
Storm Drainage Improvements on E. Pennsylvania Avenue were completed in Spring 2024. On the western side of South Church Street, improvements will include sidewalks, curb, gutter, streetlights, storm drainage, parking spaces and landscaping. 

In addition, a one-way traffic pattern is being requested from VDOT that will require additional signage and stripping. 

PROJECT BOUNDARIES:         
South Church Street: Oktoberfest Way to East Broad Way. East Pennsylvania Avenue: South Church Street to Municipal Complex.

DEFICIENCIES AND NEEDS:    
The project addresses walkability, storm water management, and other streetscape elements to improve the pedestrian and vehicular safety of the roadway.

Status Updates

PROJECT STATUS:
The design is complete, and the initial phase of improvements to the storm drainage were completed in Fall 2023. Last phase includes pedestrian improvements to be constructed beginning in Fall 2025.
 

NEXT PROJECT MILESTONE:
Construction of initial phase of storm drainage improvements have been completed.  One-way traffic striping and signage is anticipated in Summer 2025. Sidewalk construction to commence in Fall 2025.

Files & Resources

Map

Timeline

START DATE: Fall 2020

COMPLETION DATE: Fall 2026

Contact Information

Charles A. Mumaw, P.E.

Project Manager

540-755-3005 (direct)

703-728-8921 (cell) 

cmumaw [at] lovettsvilleva.gov (cmumaw[at]lovettsvilleva[dot]gov)